Lien waivers by state · Alaska
Alaska lien waiver requirements
Alaska is a non-statutory state
Alaska does not prescribe a specific or statutory lien-waiver form, so waivers may be freely worded; a written waiver signed by the claimant requires no consideration and is valid and binding under AS 34.35.117. Waivers may not cover labor, materials, services, or equipment furnished after the date the waiver is signed (advance/pre-furnishing waivers are not enforceable), and individual wage laborers (AS 34.35.120(10)) cannot waive their lien rights.
Statute: Alaska Stat. § 34.35.117 (waiver of lien rights); see also AS 34.35.050–34.35.120 (Mechanics & Materialmen liens)
Alaska lien waiver forms
| Waiver type | Statutory form? | Notarized? |
|---|---|---|
| Conditional waiver and release on progress payment | ||
| Unconditional waiver and release on progress payment | ||
| Conditional waiver and release on final payment | ||
| Unconditional waiver and release on final payment |
Requirements at a glance
Key Alaska deadlines
Alaska lien waiver FAQ
Does Alaska require a specific lien waiver form?
No. Alaska does not require a specific or statutory lien-waiver form. Parties may use their own wording; under AS 34.35.117 a written waiver signed by the claimant is valid and binding without consideration, but it cannot cover work furnished after the signing date (no advance waivers).
Do lien waivers need to be notarized in Alaska?
No. Lien waivers do not need to be notarized in Alaska to be valid — they need only be in writing and signed by the claimant (a client may still request notarization). Note that the recorded mechanics lien claim itself, by contrast, must be notarized.
Can lien waivers be signed electronically in Alaska?
Yes. Alaska has adopted the Uniform Electronic Transactions Act (AS 09.80.010 et seq.) and the federal E-SIGN Act applies, so electronic signatures on lien waivers are legally equivalent to handwritten signatures.
What is the deadline to file a mechanics lien in Alaska?
A claim of lien must be recorded within 120 days after the claimant last furnishes labor, materials, services, or equipment. If the owner records a Notice of Completion, the deadline drops to 15 days after that recording — unless the claimant had filed a Notice of Right to Lien, which preserves the 120-day period (AS 34.35.068).